What is an ADU? The Ultimate Guide to Accessory Dwelling Units

An Accessory Dwelling Unit (ADU) is a separate living space built on the same property as your main home, different from an accessory structure like a shed or workshop. In California, many homeowners build ADUs because recent state laws (like SB9) make it easier, allowing you to add this space without complicated approvals.

You can create an ADU by:

  • converting an existing structure such as a garage or attic into a fully functional living space.
  • Adding onto your current home.
  • Building a new separate structure, such as a backyard cottage.

Common reasons people build ADUs:

  • Provide extra housing for family or guests.
  • Offer independent living for older family members, adult children, or young adults.
  • Earn extra income by renting it out.
  • Set up a quiet home office.

In this guide, we'll clearly explain what an ADU is, how it's different from similar buildings (tiny homes, guest houses), ways to pay for it, and what you need to know before building one.

What is an ADU Compared to an Addition or Remodel?

In this guide, we'll clearly explain what an ADU is, how it's different from similar buildings (tiny homes, guest houses), ways to pay for it, and what you need to know before building one.

When does an addition or remodel become an ADU?

An addition or remodeled space becomes an ADU when it includes:

  • A kitchen
  • A bathroom
  • At least one sleeping area (bedroom)

For example, adding a kitchen to an existing bedroom and bathroom typically converts the space into an ADU.

Owner-occupancy requirements (California):

  • Before January 2024, property owners needed to live on-site to qualify their ADU
  • Starting January 2024, California law allows absentee ownership. Many homeowners now rent their ADUs as short-term rentals or Airbnbs.

Key Differences:

Type of Project

ADU

Regular Addition/Remodel

ADU Requirements

Kitchen, bathroom, sleeping area

No specific requirements (e.g., adding a bedroom, updating a kitchen, etc.)

Type of Project

Rentals, multi-generational housing, independent living

Expanded living space for current residents

Type of Project ADU Requirements Type of Project
ADU Kitchen, bathroom, sleeping area Rentals, multi-generational housing, independent living
Regular Addition/Remodel No specific requirements (e.g., adding a bedroom, updating a kitchen, etc.) Expanded living space for current residents
Type of Project
ADU
Regular Addition/Remodel
ADU Requirements
Kitchen, bathroom, sleeping area
No specific requirements (e.g., adding a bedroom, updating a kitchen, etc.)
Type of Project
Rentals, multi-generational housing, independent living
Expanded living space for current residents

Important Note:

If a structure is not classified as an ADU, it does not benefit from streamlined approvals and special financing available to ADUs. Homeowners not interested in these benefits can still follow traditional processes (variances, zoning changes, etc.).

ADUs can be attached directly to your home or built as separate, independent structures like apartments or guest houses.

Types of ADUs and Common Names (How They Differ)

Accessory Dwelling Units (ADUs) come in various forms, each suited for different properties and homeowner needs. Here’s a simple breakdown of each type, along with the common names people use

Detached ADU (DADU)

A Detached ADU is completely separate from your main home, built as a standalone structure on your property. Detached ADUs typically have their own utilities, entrance, and living amenities.

Common examples include:

  • Backyard Cottage
    Small, detached, one-story home located in your backyard or side yard, usually under 1,000 square feet.
  • Carriage House
    Traditionally built above a garage or storage space, these ADUs are often charming, historically inspired structures.
  • Laneway House
    Located at the rear of urban properties, usually facing an alley or laneway. These maximize space on smaller lots.
  • Tiny House
    Small, compact living units placed on a permanent foundation, connected to utilities, and compliant with building codes.

Attached ADU

An Attached ADU shares a common wall, roof, or floor with your main home. Attached ADUs typically connect through an interior hallway or door and often share utilities

Common examples include:

  • Accessory Apartment (also called Attached Apartment)
    A smaller apartment within your main home’s structure, often created by adding onto the existing home.

     

  • Garage Apartment
    An apartment created within or above a garage, sharing structural support with your main house.

     

Internal ADU

An Internal ADU is created by converting existing interior space within your main home—such as a converted garage, basement, or attic—without building outward or adding new foundations or roofing.

Common examples include:

  • Basement Apartment
    Converts a basement into a fully equipped living space with a kitchen, bathroom, and sleeping area.
  • Converted Attic
    Transforms attic space into livable square footage, requiring upgrades to insulation, support structures, and utilities.

Garage Conversion ADU

This type specifically refers to fully converting an existing garage space into living quarters. Unlike a garage apartment, it uses the entire garage area—including the concrete slab—to create a complete home.

Junior ADU (JADU)

A Junior ADU (JADU) is a smaller type of ADU (up to 500 square feet). It can be attached or detached but typically represents the smallest category of accessory dwelling units.

Quick Reference Table: ADU Types and Alternate Names

  • Short-term loan for covering construction costs, then converts into a mortgage. Sometimes the owner finances the construction with personal funds, then applies for a mortgage after completion.

Benefits of Building an ADU

Building an Accessory Dwelling Unit (ADU) offers several important benefits. These include generating extra income, creating affordable housing solutions, increasing your property’s value, and more. In fact, the numerous benefits of ADUs make them one of the smartest home improvements for California homeowners today.

Top 5 Benefits at a Glance:

  1. Extra Rental Income (typically $1,800-$3,000/month in Roseville, CA)
  2. Increased Home Value (often 20%-30% equity boost)
  3. Affordable Housing (helps solve California’s housing crisis)
  4. Flexible Housing (independent living for seniors or family)
  5. Home Office or Guest Space (private, convenient work or living area)

Benefits of Building an ADU

Building an Accessory Dwelling Unit (ADU) offers several important benefits. These include generating extra income, creating affordable housing solutions, increasing your property’s value, and more. In fact, the numerous benefits of ADUs make them one of the smartest home improvements for California homeowners today.

Who Can Build an ADU? Owner-Occupancy & Local Regulations

In California, unlike the rest of the United States, recent legislation has made it easier than ever for homeowners to build ADUs in residential neighborhoods. However, there are still important regulations and eligibility factors you should know.

Who Qualifies to Build an ADU?

Under California state laws, most homeowners can now build an ADU on their residential property. Key points include:

Lot Size:

  • No minimum lot size required statewide.
  • Local governments cannot impose restrictive lot size rules.
  • ADU size minimum is generally 150 square feet.

Setback Rules:

  • Relaxed statewide, but local regulations can vary.
  • Traditional setbacks: 15’ side, 45’ rear, 60’ front. Local rules may differ slightly, especially in dense areas.

California ADU Legislation at a Glance

Legislation

SB9

AB976

AB671

Effective Date

January 2022

January 2024

2019

Type of Project

Allows homeowners to add one ADU per lot without zoning approvals

Removes requirement for owner-occupancy (owners can rent out both primary home and ADU)

Requires local governments to allocate funds supporting ADU planning and construction

Owner-Occupancy Rules (California)

Before January 2024:

  • Property owners had to live on-site (either in main home or ADU) to legally rent out the other unit

After January 2024 (AB976):

  • Owner-occupancy no longer required. Owners can live off-site and rent both units.

Owner Occupancy Requirement

Owner lives on property

AB671

Allowed Before 2024?

Yes

No

Allowed After 2024?

Yes

Yes (new!)

Permitting, Taxes, and Fees

Adding an ADU will typically increase your property value, triggering some financial considerations:

Property Taxes:

  • Slightly higher taxes based on increased home value (usually minimal compared to equity gained).

Permit Fees:

  •  Permit fees required, but streamlined under SB9 (faster, easier approval process).

Local & HOA Regulations:

  •  Permit fees require Under state law, homeowners associations (HOAs), zoning boards, and local architectural committees typically cannot block ADUs (with few exceptions). California state laws supersede local regulations.
    
d, but streamlined under SB9 (faster, easier approval process).

Quick Eligibility Checklist for California Homeowners

Factor

Single-family residential lot

Owner occupancy

Minimum Lot Size

Setbacks

Local HOA or City rules

Allowed

Allowed statewide

Optional (after 2024)

No statewide minimum

Generally relaxed

Usually overridden by state law

Not Allowed

Commercial or industrial lo

Required (prior to 2024)

Local restrictions disallowed

Some local rules may apply

Few exceptions (historic zones, etc.)

Key Takeaways:

  • Most California homeowners qualify to build an ADU.
  • Owner-occupancy no longer required starting 2024.
  • State laws override most local restrictions, making ADUs easier to build.
  • Slight increases in taxes and permit fees are typically offset by increased home equity and rental income potential.

ADU Construction Process: From Permits to Move-In

Building your ADU follows the same essential steps as any home construction project, but California's
streamlined process helps you move forward quickly. Here’s an overview of each major step

Building your ADU follows the same essential steps as any home construction project, but California's streamlined process helps you move forward quickly. Here’s an overview of each major step

Step-by-Step ADU Construction Overview:

Step 1

Design & Planning

Step 2

Local Regulations & Permitting

Step 3

Secure Financing

Step 4

Hire a Trusted Contractor

Step 5

Construction & Inspections

Step 6

Final Move-In & Use

1. Design & Planning

Decide the type, style, and floor plan for your ADU. Consider these factors carefully:

  • Most California homeowners qualify to build an ADU.
  • Owner-occupancy no longer required starting 2024.
  • State laws override most local restrictions, making ADUs easier to build.
  • Slight increases in taxes and permit fees are typically offset by increased home equity and rental income potential.

2. Local Regulations &
Permitting (Simplified)

In Roseville and Placer County, permitting is simplified but essential:

  • Verify basic local requirements (lot coverage, setbacks).
  • Apply for a building permit through your city or county’s building department.
  • California state law streamlines permitting, so approval generally moves quickly.

Note: For detailed permitting info in Roseville and Placer County, visit our dedicated ADU Permit Requirements page

3. Secure Financing for Your ADU

Common methods to finance your ADU include:

Financing Method

Home Equity Loan (Fixed loan)

HELOC (Home Equity Line of Credit)

Construction Loan

Cash-Out Refinance

Cash Payment

Equity Sharing Agreements

Best For

Predictable monthly payments

Flexible borrowing as needed

Paying incrementally based on progress

Leveraging existing equity

Owners with substantial savings

Homeowners who prefer not to take loans

Note: For detailed information about costs, financing options, and budgeting your ADU in Roseville and Placer County, visit our dedicated ADU Costs and Financing page.

4. Hire a Trusted ADU Contractor

Your ADU contractor will manage all aspects of the construction, including:

  • Construction scheduling and management
  • Subcontractor coordination (plumbing, electrical, framing)
  • Material ordering and delivery
  • Inspections coordination

Choosing the Right Contractor (Quick Checklist):

✅  Licensed and insured

✅  Local and experienced (familiar with Roseville/Placer County)

✅  Positive reviews and references

✅  Provides clear, transparent pricing and communication

 5. Construction & Inspections (Simplified)

General stages of construction include:

  1. Site Preparation: Excavation, grading, utility connections.
  2. Foundation & Framing: Concrete slab, walls, roofing.
  3. Utilities & Systems: Electrical, plumbing, HVAC installation.
  4. Insulation & Drywall: Energy-efficient insulation and finishing.
  5. Interior Finishes: Flooring, cabinetry, fixtures.

Note: Ralh Construction handles all inspection scheduling, coordination, and compliance.

6. Final Move-In & Use

After final inspections and approvals, you’re ready to move in or start renting your ADU. Typical final tasks include:

  • Final walk-through with contractor
  • Receiving occupancy approval from your city or county
  • Setting up utilities and appliances
  • Beginning your chosen ADU use (rental, home office, family housing)

Quick Reference: ADU Construction Timeline

Common methods to finance your ADU include:

Stage

Design & Planning

Permitting

Financing

Construction & Inspections

Total Project Time

Typical Timeframe

2–4 weeks

1–3 months

2–4 weeks

4–6 months

Approx. 6–9 months

Key Takeaways:

  • The ADU process is straightforward when planned correctly.
  • California’s streamlined laws make building quicker and simpler.
  • Working with a trusted local contractor ensures smooth, hassle-free construction.
  • The overall timeline averages 6–9 months from start to finish.

ADUs as an Investment – Extra Income & Increased Property Value

Adding an ADU to your property is not only beneficial in the short term, but it can also provide substantial long-term financial advantages. Here’s a clear breakdown of the investment benefits:

Long-Term Investment Benefits

ADUs offer strong, stable long-term returns by:

  • Increasing your home’s overall equity
  • Providing consistent rental income
  • Creating options for multi-generational wealth
  • Enhancing property marketability for future resale

Typical Equity Increase:

ADU Type

Detached ADU

Attached/Internal ADU

Garage Conversion

Avg. Equity Increase

20–30%

15–25%

10–20%

Yearly Rental Income Potential (Example):

ADU Rental Rate (monthly)

$1,800

$2,500

$3,000

Annual Income

$21,600

$30,000

$36,000

Note: Even modest rental income can significantly offset mortgage payments and property expenses.

Short-Term Investment Benefits

ADUs provide attractive short-term investment opportunities through:

  • Vacation rentals (Airbnb)
  • Seasonal or short-term tenant rentals
  • Flexibility to change rental strategies based on demand or season

Example Short-Term Rental Scenario:

Use Type

Vacation/Airbnb

Short-term Tenants

Income Potential

High nightly/weekend rates

Consistent monthly income

Best Season

Summer, holidays

Year-round stability

Tip: Short-term ADU investments offer flexibility to adjust rental strategy based on market conditions and personal needs.

ADU Investment vs. Expenses (Illustration)

Here’s a clear example illustrating how rental income from your ADU can offset your housing expenses:

Without ADU

Annual Mortgage: $24,000

Income Generated: $0

Net Housing Cost: $24,000/year

With ADU (Generating $1,800/mo.)

Annual Mortgage: $24,000

Income Generated: $21,600

Net Housing Cost: $2,400/year

In this example, adding an ADU dramatically reduces your net yearly housing cost by over 90%

Long-Term Wealth and Equity Building

By owning an ADU, you create opportunities for generational wealth through:

  • Consistent property appreciation: ADUs consistently add market value.
  • Financial Security: Reliable monthly rental income provides financial stability.
  • Inheritance: Future generations benefit from increased property value and additional income potential.

ADU Investment Quick Summary Chart

Benefit

Increased Equity

Rental Income

Reduced Housing Expenses

Generational Wealth

Short-Term Rental Flexibility

Financial Impact

20-30% immediate home value increase

Consistent monthly/yearly cash flow

Offsets mortgage/property costs

Long-term financial security

Seasonal income opportunities

Who Benefits Most?

Homeowners & future sellers

Retirees, investors, families

All homeowners

Families, estate planning

Entrepreneurs, vacation rentals

Key Investment Takeaways:

  • High ROI: ADUs provide significant return on investment through equity and rental income
  • Stable Cash Flow: Consistent income can dramatically reduce overall property expenses.
  • Flexibility: Adapt rental strategy to maximize profits year-round.
  • Long-term Wealth: ADUs build generational wealth and provide financial security for your family.

ADU Floor Plans & Design Considerations

When designing your Accessory Dwelling Unit (ADU), thoughtful planning maximizes your space, enhances functionality, and increases both comfort and rental value. Here are key considerations to guide your design decisions:

Important Design Factors

To create an effective, appealing ADU, carefully evaluate:

  • Purpose & Functionality: Determine if your ADU is for rental income, family housing, a home office, or guests.
  • Space Efficiency: Maximize usability in smaller areas.
  • Accessibility Needs: Include ADA-compliant features if needed.
  • Complementing Main Home: Design choices should enhance overall property aesthetics and value.

Common ADU Layout Types

Open Floor Plans:

  • Spacious feel, fewer walls, and multifunctional rooms
  • Ideal for small ADUs (studios or one-bedroom units)
  • Features: Vaulted ceilings, large windows, natural lighting

Traditional Floor Plans:

  • Clear separation of rooms (living area, bedroom, kitchen)
  • Greater privacy and defined spaces
  • Ideal for multiple occupants or longer-term living situations

Open Floor Plan Advantages

Feels larger & brighter

Flexible furniture layouts

Modern, airy appeal

Traditional Floor Plan Advantages

Enhanced privacy

Defined functional areas

Comfortable long-term living

Space-Saving &
Efficiency Features

Incorporating efficient design features greatly enhances the usability of smaller ADUs. Popular features include:

  • Pocket Doors: Save floor space usually taken by door swings.
  • Murphy Beds: Provide flexible sleeping options, freeing up floor space.
  • Built-in Storage: Cabinets, closets, and shelving to maximize storage.
  • Loft Spaces: Additional sleeping or storage space without expanding footprint.
  • Compact Appliances: Space-efficient kitchenettes and laundry units.

Best Space-Saving Ideas (Quick Reference):

Feature

Murphy Beds

Loft Sleeping Areas

Built-in Storage

Pocket Doors

Compact Kitchenettes

Benefit

Flexible sleeping area

Adds usable floor space below

Reduces clutter, maximizes room

Saves wall/floor space

Fully functional, less footprint

Best ADU Types

Studios, guest rooms

Detached cottages

All ADU types

Small & compact ADUs

Studio or Junior ADUs

ADA Accessibility Considerations

If planning an ADU for senior living, mobility-challenged family members, or long-term rental, consider these accessibility improvements:

  • Wide doors & hallways (min. 36 inches recommended)
  • Roll-in showers and accessible bathroom features
  • Lever-style door handles and faucet controls
  • Non-slip flooring and grab bars
  • Single-level floor plans or ramps for easy entry

Attic & Storage Opportunities

ADUs connected to your main house (attached ADUs) offer valuable attic space for additional storage, increasing functionality and market value. Ensure proper fire barriers are installed per building codes when sharing roofs or walls.

Best Space-Saving Ideas (Quick Reference):

Floor Plan Type

Studio

One Bedroom

Two Bedrooms

Typical Size (Floor Area)

150–400 sq. ft.

400–700 sq. ft.

700–1200 sq. ft.

Ideal Use Case

Single occupant, rental, home office

Couples, guest housing

Families, multi-generational living

Note: Local regulations may limit maximum ADU size; typically, 1200 sq. ft. detached ADUs are the largest allowed.

 Key Design Takeaways:

  • Choose a floor plan matching your goals (rental, family housing, home office).
  • Prioritize efficient, space-saving design to maximize functionality.
  • Incorporate ADA accessibility if needed for long-term usability.
  • Thoughtful design directly contributes to higher rental income and property value.

Frequently Asked Questions About ADUs

Currently, laws are very friendly for building an ADU on your own property. If you have a backyard (and now even a front yard) you can an ADU! State laws supersede any city, county, and HOA restrictions.

The largest detached ADU you can build on your property is 1200SQFT. If you are building an attached ADU, which is a JADU (Jr ADU) then it can not be 50% larger than the main residence’s square footage.

You will need to obtain a building permit to begin construction on your ADU. However, there are multiple requirements to get you there which include: fire approval letter, School letter, Sewer, water etc. It can take anywhere from 2-4 months to get your permit after initially filing.

It depends! This varies by the local jurisdiction that your property is located. In areas with already dense residential populations, this will always come up. For example, Cities are more strict in parking requirements rather than counties with bigger lot sizes. If you are in the City of Sacramento, Citrus Heights, or other areas with similar density you can expect to meet parking requirements.

Building an ADU can cost anywhere from 175k all the way up to 400k+ depending on a lot. Some of the factors you should look into is how is the area that you are planning to use as the foundation for your ADU? Is it sloped? Does that require extensive excavation and grading work? Is the soil filled with rock and granite? Where are your utility tie connection points? What kind of design are you looking for: Spanish, Modern, Farmhouse?
As you can see, so many factors play into the final pricing of your ADU so no one number fits all.

Fees that need to be budgeted for are plan check fees, impact fees if you are building an ADU greater than 749 SQFT, Fire Sprinkler and Solar Fees.
These will all depend on what your local jurisdiction will want, so it is best to work with an ADU builder who has experience and is well versed in this type of work.

(Can I use a home equity loan, construction loan, or are there special ADU loan programs or grants?) Financing is one of the most crucial pieces to the puzzle when it comes to building your ADU. You can go about this a few ways, see bullets below;

  • HELOC – Utilize the equity in your property and pull a line of credit to help finance your build. 
  • Cash Out Refi – Another way to utilize the equity in your property to help finance your ADU. 
  • Construction Loan – You can use a construction loan to build an ADU, yes you actually can. Although it has costs involved with it, this option may be best for investors or someone looking to build multiple ADU’s. 
  • Cash – If you have the resources available you can pay directly out of pocket. 

You can expect your property value to rise and earn a very strong rental income from your ADU. Although appraisers and the real estate market are still learning the value and how to appraise ADU’s, they still do add value to your property immediately. An average 2 bed 1 Bath can rent from $2,000- $2,700. Crazy, right? Well if you look at what apartments are costing you nowadays those numbers don’t sound too bad. Especially when you consider you are not worrying about sharing walls with your neighbors or walking up a flight of stairs with your groceries.

From start to finish, you are looking at a 6-9 month time frame. The construction process usually moves fairly quickly in comparison to obtaining plans/design/permit.

Here are the few main steps:

  • Design – Working with a reputable Architect who has experience in ADU’s and local jurisdictions ensures this step goes smoothly. 
  • Permitting – Working with the planning and building department to meet all requirements needed to obtain your construction permit. 
  • Construction – Using a licensed General Contractor who will navigate the construction process which includes: scheduling, inspections, subcontractor management, material deliveries, recycling requirements, and much more.

The reality is, when you are building your ADU your backyard turns into a short term job site. Like any job site you may have seen or driven by, there is material that needs to be stored, need to have temporary restrooms for all the workers, etc. That being said, it can be a disruption if expectations are not clearly defined. What we do here at Ralh construction is establish a barrier, usually throw snow fencing or something of that nature, so the homeowner can still have their privacy and space.

Due to new code requirements, all electrical panels need to be upgraded to be able to provide power to the ADU and then the existing dwelling on the property.

For sewer and water tie ins, that is dependent on your property. If you are required to have Fire Sprinklers, then you may need to upgrade your water line to account for the amount of water that is needed for both structures. As far as sewer tie ins go, most times you will not need to update your sewer line (unless your structure is very old). However if you are on a septic system on your existing dwelling, you will need to either upgrade to a bigger tank or add a different septic system for the ADU.

The qualifications and credentials you should be looking at - there is a few of them.

To begin, is your contractor local or from out town? I would almost always recommend working with a contractor from your local area, this will lead to them being very familiar with the inspections and requirements needed to ensure a smooth painless construction process.

Do they have examples of completed work? You don’t need to see a 100 projects completed, but at least being able to see photos of one or even walk a job in progress or a completed project (if available) is highly recommended.

Other things to look at, are there trucks wrapped with their company information? This shows they are proud of the work they do and hold true to their brand.

Last but not least, can you view this contractor as a teammate in your ADU journey? Construction has its ups and downs, no matter who you work with. Ensuring you are working with someone who has your best interest is CRUCIAL to project success.

You can look up the contractor and information about their license on the California State License Board website, check google reviews, view social media, and ask to see pictures of their portfolio.

Some red flags that you should look out for when picking you contractor is the follows:

  • Unlicensed – Run as fast as you can! If something goes wrong, the homeowner is held liable for all injuries/damages. 
  • No company branding
  • Asking for a 50% deposit to get the project started – legally, it can only be 10% or $1000. Whichever comes first. 
  • No past reviews/Social Media/Internet Presence – these are your fly by night contractors, avoid these at all costs. 
  • Being unorganized as a contractor is a big red flag. Do they show up on time? Do they do the things they said? How can you trust someone to manage and organize your money and all the subcontractors if they are not organized themselves
  • Lowest bid – they are lowest bid for a reason. Unethical practices and cutting corners are the only way they are beating out pricing.

It depends on who you work with! Some contractors only handle the construction process, leaving the design and permitting process on the homeowner.

At Ralh Construction, we handle all design, permitting, and construction required for your ADU. Our goal is to make this as seamless as possible for the homeowner.

(How can I make a studio or one-bedroom ADU feel more open and functional?)

There are a couple ways you can achieve maximizing your space for your ADU. One way would be to high ceilings, nine feet ceilings for example. This makes the structure feel much more open than what it actually is. Another way is to have vaulted ceilings, this is a great way to maximize space, especially for smaller units such as studios.

We can build to whatever design you have in mind! We also offer a pre-designed plan for those who want to keep the design process simple and move quickly.

PRO TIP: Hire an interior designer if choosing to do a custom design, this can save you thousands of dollars and potentially your marriage….

All of the building materials and methods that are used are energy efficient and up to California building standards, meaning we have this covered for you! There are other ways to increase your energy efficiency such as higher rated insulation, using higher efficiency windows, and adding timers to switches to help avoid any lights being left on!

There are a few differences between building on site vs. fabricating off site. One of the main differences is the control of your design and footprint of your ADU. When building on site, you can determine what you want your ADU to look like however most Pre-Fab options, you are limited to design options.

Another thing to consider, Pre-Fab units still require all excavation, grading, and foundation work to occur. So although it may seem like there is less work involved, that is not the case.